How long should a startup website relaunch take?
A startup website relaunch should take 3 to 6 weeks for a site of up to about 20 pages, and up to 8 weeks when it's tied to a brand change or a launch campaign. Most of that time goes on decisions, not building, so the fastest relaunches lock positioning and pages in the first week.
Key takeaways
- Our recent relaunches took between 3 and 8 weeks from kickoff to a live site.
- Hims & Hers Australia went live in 5 weeks: about 20 pages moved from Juniper to the Hers brand, live on the day of the rebrand.
- PassEntry moved from WordPress to a new Framer site in under 6 weeks, built to match its €6.2M Series A.
- For HackerRank's Chakra launch, we went from version 6 to the final homepage in about 10 days by running several page variants live at once.
- Fixed dates help. Plan backwards from the launch day and agree the page list and messaging before design starts.
How long do relaunches actually take?
Here are five recent relaunches, from kickoff to live:
- HackerRank, Chakra launch: 8 weeks, from a four-hour working session in San Francisco to a new Chakra page, a new hackerrank.com homepage and billboard creative, all live in the same week. The site went live three days ahead of the billboards.
- Hims & Hers Australia: 5 weeks. We set up and cleaned up Contentful, reskinned about 20 pages and added tracking, then launched hers.com.au on the day Juniper became Hers.
- PassEntry: under 6 weeks, from a crowded WordPress site to a new Framer site with clearer messaging for enterprise buyers.
- Kimia: a new brand, website and design system in under a month, in Kimia's own words.
None of these took three months. When a relaunch runs long, it's usually because decisions are waiting on someone.
What decides how long yours takes?
Four things, in order of impact:
- How fast decisions get made. The page list, the main message and who signs off. Lock these in week one.
- Whether the brand is changing. A reskin on an existing brand is faster than a new brand and a new site together.
- How many pages and templates. Twenty pages built from five templates is faster than ten one-off pages.
- The system underneath. A clean CMS speeds up the build. At Hims & Hers we fixed the Contentful setup before reskinning a single page.
How did the Chakra homepage go from version 6 to final in 10 days?
We changed how we built it. For HackerRank we tested Sherpa alongside Framer before committing, and Sherpa won: it matched our Figma designs 1:1, and the site runs on Astro, which keeps pages light and fast to load. Because it's real code underneath, we could add GSAP animation and customise everything.
Three things made the speed possible:
- Variants live at the same time. Several versions of a page, each on its own preview link, so the team compared real pages instead of mockups.
- Comments on the page. We left feedback straight on the preview site, and the next round was built from it.
- Our own motion tools. We built internal tools to try many animations and section designs side by side and keep what looked best.
The result held up. Try Chakra conversion rose about 200 basis points and peaked 40% above its best before launch.
What should the timeline look like?
For a site of up to about 20 pages on an existing or refreshed brand:
- Week 1: positioning, messaging and the page list agreed. Tracking plan written.
- Weeks 2 to 3: page designs, with real copy, reviewed as live previews.
- Weeks 3 to 5: build, content entry, tracking and SEO and AI search basics: clean HTML, schema, llms.txt.
- Final week: QA on mobile and desktop, then launch, with redirects from the old URLs.
Add 2 to 3 weeks if the brand is new, and plan backwards from any fixed date.
What should a relaunch include beyond the design?
Three things that decide whether the new site brings in demos:
- Messaging for the buyer you sell to now, which has often changed since pre-seed.
- Tracking live at launch, so every demo request has a source from day one.
- A site built for search and AI search from the start, so you don't rebuild it six months later.
Our Relaunch offer runs 4 to 6 weeks and covers all three.
Questions founders ask
How long does a website redesign take for a startup?
Usually 3 to 6 weeks for up to about 20 pages, and up to 8 weeks if it comes with a new brand or a launch campaign.
Can a startup website be rebuilt in two weeks?
A focused rebuild of a few key pages on an existing brand can be. For HackerRank we went from version 6 to the final homepage in about 10 days, inside a wider 8-week launch.
Should we rebrand and rebuild the site at the same time?
If the company has changed, yes, but add 2 to 3 weeks and agree the positioning first. Kimia got a new brand, website and design system in under a month this way.
What slows a website relaunch down?
Late decisions on messaging, the page list and sign-off, and a messy CMS underneath. Lock decisions in week one and fix the content system before reskinning pages.